INSTANT UPDATE

Battle of the Maroons 2022 - KCK 127/10 and 199/10 - DRC 269/10 and 34/4 (match drawn)

Renovation of Band Room - Project 2016

Hello Brothers

It’s a year since we successfully completed our OBU Group’s last project. And now it’s the time for the next …

This year our executive committee studied carefully about many proposals and came up with a whole new idea! That is to renovate the Western Band Room, Donate uniform for the Eastern Band and to build an open mini arena for the Eastern band to practice.



Present Situation
The present situation of the Eastern Band Room is very sad. The wall plaster is damaged, the cupboards are corroded etc ..


Also the uniforms.. Present uniform sets are aged and damaged beyond repair.

The Estimate
After the on-sight inspection carried out together with MIA Mr Dammika under the guidance of our principal a rough estimate was prepared.

Cost of construction of mini arena  – Rs 450 000.00
Cost of uniforms for the Band         - Rs 400 000.00
Cost of renovation of Band room    – Rs 50000.00
Total Cost                                   – Rs 900000.00



It’s time for us to stand tall and do something for the Alma Mater !
(Please stay tuned for updates)


Bank account details of our group

Bank : Seylan Bank - Gampola Branch
Account No : 025033536300001
For any further information on this project please feel free to contact  
Basnayake (Buzz) - 0773 796047, Dilshan - 0718 227682, Anjula - 0777 875165

Progress of Day 01

 The construction of mini arena has been started. Excavation works in progress. Due to the GCE A/L exams it is hard to find a time-slot for the construction.








1 comment:

Anonymous said...

its done ,,,,buzzzz